Skip to content

   

Prince George to Terrace Capacitors Project

Capacitor station
Capacitor Station

What's new

Work is ongoing at the three capacitor station sties. Construction of the Saranovich and Palling capacitor stations is expected to be complete in fall 2026 and construction of Walcott Capacitor Station is expected to be complete in fall 2027.

The Government of Canada is investing $96.95 million in the Prince George to Terrace Capacitors Project as part of a larger federal investment of nearly $157 million for eight BC Hydro projects. This funding is being provided through the Green Infrastructure stream of the Investing in Canada Infrastructure Program, which supports the reduction of greenhouse gas emissions and the expansion of clean energy.

Bilingual English and French Prince George to Terrace Capacitors Project Government of Canada contribution sign: $210 million dollars.

We're working to increase the transfer capacity of the existing 450 km, 500 kilovolt (kV) transmission lines from Prince George to Terrace by constructing three new capacitor stations through the Prince George to Terrace Capacitors project:

  • Saranovich Capacitor Station near Vanderhoof
  • Palling Capacitor Station near Burns Lake
  • Walcott Capacitor Station near Telkwa

Prince George to Terrace Capacitors project map.
Prince George to Terrace Capacitors project map.

Select the map [PDF, 1.8 MB] to view it at a larger size.

We're also adding a transformer to Skeena Substation near Terrace to decrease the 500 kV electricity to voltages suitable for our customers. The work is entirely within the substation fence and expansion is not required.

A number of industries in the North Coast such as mining and liquefied natural gas (LNG) developments have requested power from us. We need to increase capacity along the existing 500 kV transmission line between Prince George and Terrace to meet the customers' needs.

A capacitor station contains equipment to boost the amount of electricity that a transmission line can carry. These stations are fenced, outdoor facilities that must be constructed on flat land, adjacent to or near the existing transmission line. Capacitor stations can significantly increase the capacity of the existing transmission line in a cost-effective, safe, and reliable way.

All three capacitor station sites have been prepared for station construction.

Concrete foundation installation for equipment and buildings is complete at Saranovich and Palling capacitor stations with electrical equipment installation and commissioning activities underway. Concrete foundation works are underway at Walcott Capacitor Station.

Additional detail on work completed to date and upcoming work is provided for each station below.

The expected overall project in-service date is 2028.

Saranovich Capacitor Station

Work to date:

  • 2022 – Tree clearing
  • 2023 – Access road construction
  • 2023 – 500 kV transmission tower
  • 2024 – Site preparation
  • 2025 – Civil foundation construction and start electrical installation
  • 2026 – Continue electrical equipment installation and commissioning

Upcoming work:

  • 2026 – Complete full station build and commissioning
Construction Progress at Saranovich Capacitor Station.
Construction Progress at Saranovich Capacitor Station.

Palling Capacitor Station

Work to date:

  • 2022 – Tree clearing
  • 2023 – Access road construction
  • 2023 – 500 kV transmission tower
  • 2024 – Site preparation
  • 2025 – Civil foundation construction and start electrical installation
  • 2026 – Continue electrical equipment installation and commissioning

Upcoming work:

  • 2026 – Complete full station build and commissioning
Construction progress at Palling Capacitor Station.
Construction progress at Palling Capacitor Station.

Walcott Capacitor Station

Work to date:

  • 2024 – Tree clearing
  • 2024 –Access road construction
  • 2024 – 500 kV transmission tower
  • 2024 – Site preparation
  • 2024 – 138 kV line relocation
  • 2025 – Start construction of civil foundations

Upcoming work:

  • 2026 – Complete civil foundations, complete control building, and start electrical equipment installation
  • 2027 – Complete full station build and commissioning
Walcott Capacitor Station Site.
Walcott Capacitor Station Site.
Walcott Capacitor Station – April 2026.
Walcott Capacitor Station – April 2026.

Skeena Substation

Work to date:

  • 2024 – Start construction of civil foundations for 500kV & 287kV equipment
  • 2025 – Continue civil foundations and concrete work and start electrical work

Upcoming work:

  • 2026 – Complete installation and commissioning of transformer and associated equipment
East view of the 500kV yard at the Skeena Substation.
East view of the 500kV yard.
Transformer placed on pad.
Transformer placed on pad.

Contact us

If you'd like to learn more about the project, please contact us at:

Email: projects@bchydro.com
Phone: 604 623 4472
Toll free: 1 866 647 3334