Skip to content

Glenannan to Terrace Transmission Project

Transmission towers and lines running through a forest past a lake.

We're planning to add new 500 kilovolt (kV) transmission lines from Glenannan Substation near Fraser Lake to Skeena Substation in Terrace to meet increasing demands for clean electricity in northwest B.C. Learn more about our Glenannan to Terrace Transmission (GTTT) project below.

What's new

March 2024 – Join us at an open house

Join us at an upcoming open house for an update on the Glenannan to Terrace Transmission project and other North Coast electrification initiatives.

Drop by any of these locations between 4 and 7 p.m. on the dates listed. No registration required for in-person events.

Houston
Tuesday, March 12 
Community Futures
2430 Butler Ave
Smithers
Wednesday, March 13
Prestige Hudson Bay Lodge
Alpine Room
3251 East Highway 16
Terrace
Thursday, March 14
Sportsplex
Banquet Room
3320 Kalum Street
Fraser Lake
Tuesday, March 19
Royal Canadian Legion Branch 274
165 Chowsunket Street


At the Houston, Smithers, and Terrace open houses, we’ll provide an overview of the Prince George to Glenannan Transmission (PGGT) project. Detailed routing information for both PGGT and GTTT will be available at the Fraser Lake open house.

We’re also hosting additional open houses for the PGGT project.

Virtual presentations available

If you can’t attend an in-person event, we’re having two virtual events. To register for a virtual presentation, email us at projects@bchydro.com by March 19.

Thursday, March 21
6:30 to 8 p.m.

Tuesday, March 26
6:30 to 8 p.m.

Demand is growing from customers in the North Coast area for clean, reliable power to support electrifying their operations to reduce greenhouse gas emissions.

The current 500 kV transmission infrastructure from Williston Substation near Prince George to Skeena Substation near Terrace is reaching its capacity limit and electricity from the Prince George to Terrace Capacitors project, which is currently under construction, is already fully subscribed. We need to expand our transmission system to meet projected demand.

We're planning to add new transmission lines and associated infrastructure from Glenannan Substation to Skeena Substation:

  • An approximately 130 km line from Glenannan to Telkwa substation, and
  • An approximately 145 km line from Telkwa substation to Skeena substation.
  • Expanding Skeena Substation to accommodate required equipment.
  • Expanding Palling and Walcott capacitor stations (CAP 2 and 3) to allow the line to carry more electricity reliably.

North Coast Electrification project map

North Coast Electrification project map

Select the map [PDF, 1.7 MB] to view it at a larger size.

This project is part of the North Coast electrification initiative which also includes the Prince George to Glenannan Transmission (PGGT), Prince George to Terrace Capacitors and Northwest Substation Outage Mitigation projects, thermal upgrades to the existing 500 kV lines from Williston Substation to Skeena Substation, potential new transmission infrastructure north, south and west of Terrace and customer interconnection projects.

We've identified a route corridor shown in the figures below and are working to identify route options where the new transmission line cannot parallel existing lines between Telkwa Substation and Skeena Substation.

Glenannan Substation to Telkwa Substation

The proposed transmission line routes in this area will generally parallel the existing transmission lines on the north side of the lines.

Glenannan Substation to Telkwa Substation project map

Select the map [PDF, 3.2 MB] to view it at a larger size.

Telkwa Substation to Skeena Substation

The proposed transmission line routes in this section have not been determined. They may be north or south of the existing line and may deviate from the existing lines in certain areas.

 

Telkwa Substation to Skeena Substation project map

Select the map [PDF, 2.7 MB] to view it at a larger size.

Key dates Activity
2022 to spring 2024
  • Start desktop and field studies
  • Assess route and site options
  • Select route location
2024 to 2026
  • Complete studies and design work
  • Acquire property rights
  • Seek required regulatory approvals
2026
  • Start construction
Fall 2030
  • Target in-service date


In March 2024, we’re hosting virtual and in-person open houses in Houston, Smithers, Terrace, and Fraser Lake. See the top of the page for details. We’ll post the presentation materials here afterwards.

Early engagement with our Indigenous partners is also underway, and this aligns with our commitment to co-design the environmental review and explore Indigenous co-ownership of the proposed new transmission lines, as well other means of Indigenous participation.

In May 2023 we held open houses in Terrace, Smithers, Burns Lake and Fraser Lake to introduce North Coast electrification, including the GTTT project. We had a good turnout at the open houses and received feedback on what we should consider when looking at routing options, which we're considering in the development of the route and options.

Feel free to contact us at any time to discuss or provide feedback about the GTTT project, including the routes under consideration.

We look forward to discussing our plans with you.

Contact us

If you'd like to learn more about the project or provide feedback on the project, please contact us at:

Email: projects@bchydro.com
Toll free: 1 866 647 3334

Get email updates

Receive updates and information about North Coast electrification and the associated projects by subscribing below. If you'd like to sign up to receive updates about the North Coast Expression of Interest, please visit the Expression of Interest page.

Subscribe