Skip to content

North Coast Transmission Line Phase 2: Glenannan to Terrace Transmission

Transmission towers and lines running through a forest past a lake.

We're proposing to build the North Coast Transmission Line: Phase 2 to add new 500 kilovolt (kV) transmission lines and associated infrastructure from Glenannan Substation near Fraser Lake to Skeena Substation in Terrace to meet increasing demands for clean electricity in the North Coast area.  

What's new

June 2025 – Open houses 

Join us at an open house to learn about the North Coast Transmission Line.

At the open houses, we’ll share our work to identify leading routes for Phase 1 and Phase 2, and our other activities in the North Coast area. 

Learn about Phase 1: Prince George to Glenannan Transmission

Location Date Address
Prince George Monday, June 9
4 to 7 p.m.
Central B.C. Railway & Forestry Museum
850 River Road
Vanderhoof Tuesday, June 10
4 to 7 p.m.
Integris Community Center
Multi-purpose Room
186 Columbia Street West
Fraser Lake* Wednesday, June 11
4 to 7 p.m.
Professional Building
298 McMillan Ave

*Phase 2 information will also be available at the Fraser Lake open house.



Learn about Phase 2: Glenannan to Terrace Transmission

Location Date Address
Terrace Thursday, June 12
4 to 7 p.m.
Sportsplex
Banquet Room
3320 Kalum Ave
Smithers Tuesday, June 17
4 to 7 p.m.
Prestige Hudson Bay
Lodge & Conference Centre
3251 Hwy 16 East
Houston Wednesday, June 18
4 to 7 p.m.
Houston Community Hall
2302 Butler Ave
Burns Lake Thursday, June 19
4 to 7 p.m.
Lakes District Secondary School
Multi-Purpose Room
685 Yellowhead Hwy 16 W


Online open houses

Can’t make an in-person event? We’re having two online open houses: June 23 and 24 from 6:30 to 8 p.m. Register by emailing us at projects@bchydro.com by June 22.

We look forward to discussing our work with you.

We’re bringing more clean, reliable electricity to the North Coast to foster economic growth and enable our customers to use clean electricity to power their operations and reduce greenhouse gases.

The current 500 kV transmission infrastructure from Williston Substation near Prince George to Skeena Substation near Terrace is reaching its capacity limit and electricity from the Prince George to Terrace Capacitors project, which is currently under construction, is already fully subscribed. We need to expand our transmission system to meet projected demand.

Through North Coast Transmission Line Phase 2 we're proposing to:

  • Build approximately 130 km of new, 500kV transmission line from Glenannan to Telkwa Substation.
  • Build approximately 145 km of new, 500kV transmission line from Telkwa Substation to Skeena Substation.
  • Upgrade Glenannan and Telkwa substations.
  • Expand Skeena Substation to the north.
  • Expand Palling and Walcott capacitor stations to the northwest.
  • Add fibre optic cables on new or existing transmission lines.

North Coast Transmission Line Phase 1: Prince George to Glenannan Transmission covers the area from Williston Substation to Glenannan Substation.

We’re also proposing  upgrades to the existing 500 kV lines from Williston Substation to Skeena Substation, as well as  new transmission infrastructure north of Terrace and in Prince Rupert. We’re also continuing discussion with current and potential customers to identify whether additional infrastructure will be required south or west of Terrace.

North Coast Transmission System Expansion map

North Coast Electrification project map

Select the project map [PDF, 1.9 MB] to view it at a larger size.

We've identified a route corridor shown in the figures below and are working to identify route options where the proposed new transmission line can't parallel existing lines between Telkwa Substation and Skeena Substation.

Glenannan Substation to Telkwa Substation

The proposed transmission line routes in this area will generally parallel the existing transmission lines on the north side of the lines.

CS-3768-GTTT Route Options_5L065_Maps_36x24-feb27

Select the map [PDF, 72.1 KB] to view it at a larger size.

Telkwa Substation to Skeena Substation

We expect to present the leading route (i.e., route for further study) for the western end at open houses in June and will continue studies on that route moving forward. We continue to discuss routing options in the Telkwa area (i.e., Bulbous Toe area) with First Nations and will identify a leading route in that area at a future date.

GTTT corridor and route options map - Telkwa to Skeena

Select the map [PDF, 132.6 KB] to view it at a larger size.

Key dates Activity
Fall 2022 to fall 2025
  • Start desktop and field studies
  • Assess and select route and station locations
2025 to 2027
  • Complete studies and design work
  • Confirm workforce accommodation
  • Seek required regulatory approvals
  • Acquire property rights
Fall 2026
  • Start construction (clearing and access)
Mid-2032
  • Target in-service date

We’re hosting open houses in June 2025 with a focus on the North Coast Transmission Line.

Engagement with our Indigenous partners is also underway, and this aligns with our commitment to co-design the environmental review and explore Indigenous co-ownership of the proposed new transmission lines, as well other means of Indigenous participation.

Feel free to contact us at any time to discuss or provide feedback about North Coast Transmission Line: Phase 2.

We look forward to discussing our plans with you.

Contact us

If you'd like to learn more about the project or provide feedback on the project, please contact us at:

Email: projects@bchydro.com
Toll free: 1 866 647 3334
 

Get email updates

Receive updates and information about North Coast transmission system expansion and the associated projects by subscribing below.

Subscribe