Skip to content

   

North Coast Transmission Line Phase 1: Prince George to Glenannan transmission

Transmission lines running over a field and trees

We're building the North Coast Transmission Line Phase 1, which will add new 500 kilovolt (kV) transmission lines and associated infrastructure from Williston Substation near Prince George to Glenannan Substation near Fraser Lake. The project will support economic development and help meet the growing demand for clean electricity in the North Coast area.

What's new

Join us at an upcoming open house to learn about North Coast Transmission Line Phase 1 and our other related activities, meet the project team, ask questions, and share your feedback.

Drop in anytime between 4 p.m. and 7 p.m.
 

Prince George

Tuesday, June 2
Prince George Conference and Civic Centre
808 Canada Games Way

Vanderhoof

Wednesday, June 3
Integris Community Centre
Multi-purpose Room
186 Columbia Street

Fraser Lake

Thursday, June 4
Professional Building
298 McMillan Avenue

Can't make an in-person event?

Please join a virtual open house on Tuesday, June 9 from 6:30 p.m. to 8 p.m. Please register at projects@bchydro.com by June 8.

We’re bringing more clean, reliable electricity to the North Coast to foster economic growth and enable our customers to use clean electricity to power their operations and reduce greenhouse gases.

The current 500 kV transmission infrastructure from Williston Substation near Prince George to Skeena Substation near Terrace is reaching capacity and electricity from the Prince George to Terrace Capacitors project, which is currently under construction, is already fully subscribed. We're proposing to expand our transmission system to meet projected demand.

Through North Coast Transmission Line Phase 1: Prince George to Glenannan Transmission, we're proposing to:

  • Build approximately 165 km of new, 500 kV transmission line from Williston Substation to Glenannan Substation
  • Expand Williston Substation to the east
  • Expand Glenannan Substation to the southwest
  • Expand Saranovich Capacitor Station to the west
  • Add fibre optic cables on new or existing transmission structures.

North Coast Transmission Line Phase 2: Glenannan to Terrace Transmission, covers the area from Glenannan Substation to Skeena Substation.

We're also proposing upgrades to the existing 500 kV lines from Williston Substation to Skeena Substation as well as new transmission infrastructure north of Terrace and in Prince Rupert. We're continuing discussion with current and potential customers to identify whether additional infrastructure will be required south or west of Terrace.

North Coast Transmission System Expansion map

North Coast Electrification project map

Select the project map [PDF, 6 MB] to view it at a larger size.
 

In 2023 we identified a proposed route corridor for Phase 1 that included options along two parts of the route as shown in the figure below. 

PGGT route corridor and options

Prince George to Glenannan route corridor and options

Select the project map [JPG, 1.5 MB] to view it at a larger size.

Since then, we've evaluated the options by considering several factors as well as input from First Nations and stakeholders. We presented the southern route option as the leading route (i.e. the route for further study) for the west end at the June 2025 open houses and have now identified the route travelling directly west from Williston Substation as the leading route at the east end.

Key dates Activity
Fall 2022 to 2025
  • Desktop and field studies
  • Assess and select route and station locations
2023 to 2026
  • Complete studies and design work
  • Confirm workforce accommodation sites
  • Seek required regulatory approvals
  • Acquire property rights
Summer 2026
  • Construction begins
Fall 2030
  • Target in-service date

 

We began engaging with communities along Phase 1 of the line in 2023, during our early project planning. We will continue to share updates as we move toward and through construction.

We are also working with our First Nations partners. This supports our commitment to co-design the environmental review and explore First Nations co-ownership of the North Coast Transmission Line, along with other opportunities for Indigenous participation.

As planning for the proposed projects continues, we'll host more open houses and other events so we can share updates and hear your feedback.

Get in touch

If you'd like to learn more about the project or provide feedback, please contact us at:

Email: NCTLproject@bchydro.com
Toll free: 1 866 647 3334
 

Get email updates

Receive updates and information about North Coast transmission projects by subscribing below.

Subscribe