Skip to content

Newell Substation upgrade

Newell Substation is located at the corner of Kingsway and Griffiths Drive in Burnaby.
Above: Newell Substation is located at the corner of Kingsway and Griffiths Drive in Burnaby.

We're upgrading Newell Substation to improve reliability, address safety risks, and meet projected load growth. This will allow us to continue to provide reliable electricity to about 59,000 homes and businesses in southern Burnaby as well as to other substations.

What's new

Concrete pouring and extended work hours

As part of the ongoing upgrades at Newell Substation, we'll be pouring concrete for the foundation of the new feeder building at the northeast corner of the substation on Thursday, October 15, 2026. Because the concrete foundation must be poured continuously, the work must be completed in a single day.

To complete the concrete pour, crews will be working extended hours on the scheduled pour date only. Site set-up activities may begin as early as 5 a.m. with concrete deliveries occurring throughout the day. Depending on site conditions and construction progress, work may continue until 8 p.m.

If the work cannot proceed as scheduled due to weather or other unforeseen circumstances, Tuesday, October 20, 2026 has been identified as a contingency date.

During the concrete pour, nearby residents may notice increased construction traffic and noise as concrete pump trucks, construction vehicles and crews access the substation via Beresford Street.

Please use caution when travelling through the area and follow all posted signage and directions from traffic control crews.

We appreciate your patience and understanding as we complete this important work.

Traffic and pedestrian impacts

Temporary lane closures and pedestrian detours are in place along portions of Kingsway and Griffiths Drive to support construction activities. While active construction will generally occur Monday to Friday from 7 a.m. to 5 p.m., traffic impacts, lane closures and pedestrian detours will remain in place around the clock until this phase of work is complete.

Tree removal and replacement

One tree on Griffiths Drive near Kingsway is being removed to accommodate required underground infrastructure. To offset this impact, two new trees will be planted following project completion. Additional replacement planting is also planned for trees removed earlier in the project, with details to be confirmed as landscaping plans are finalized.

Newell Substation, located at the corner of Kingsway and Griffiths Drive in Burnaby, was built in stages from 1946 to 1955. The substation has been operating reliably for almost 70 years. Newell Substation is connected to seven other substations and serves about 59,000 customers (about 66% residential, 24% commercial, and 11% industrial). The substation takes high-voltage electricity from transmission lines and converts it to the voltages needed to supply power to customers.

We're planning to remove old outdoor equipment that's in poor condition (labelled Feeder Section to be removed in the figure below) and replace it with modern equipment housed in a new feeder building. We'll also replace one of three transformers at the substation as it's reaching end-of-life and make required upgrades to other equipment at site.

Newell substation upgrade project map

Newell substation upgrade project map

Select the project map [PDF, 821 MB] to view it at a larger size.

We'll also install underground infrastructure in Griffiths Drive to the east of the new feeder building and interconnect with existing infrastructure north of the site fence. We'll determine the specific location of the infrastructure and interconnections as studies progress.

Some land outside the fence on the south side of the substation will be used for contractor parking and work zone. During construction a walking path will be available but it will be located further south, closer to the road. After the upgrades are complete, we'll restore the sites not needed for future project work.

These upgrades will ensure that Newell Substation can continue to provide reliable electricity supply to residents, businesses, and other substations.

New feeder building

The new feeder building will be located on the northeast corner of the substation site (see figure above). This location was selected after considering:

  • Safety
  • Constructability
  • Ability to connect to existing equipment
  • Environment
  • Community impacts
  • Cost

Locating the building on the northeast corner:

  • Keeps the building within the existing property line,
  • Doesn't have permanent impacts to the greenspace south of the fence line,
  • Is further from residences, and
  • Is more cost effective.

Design of the new building is underway and current renderings are shown below.

Rendering of the gas-insulated switchgear building.
Above: Rendering of the gas-insulated switchgear building.
Newell substation - Rendering of the site looking northwest
Above: Rendering of the site looking northwest.
Rendering of the street view on Kingsway in Burnaby.
Above: Rendering of the street view on Kingsway in Burnaby.

Key datesActivity
Fall 2025

Vegetation removal.

Fall 2025

Site preparation begins with bumping out the retaining wall in the northeast corner.

Summer/fall 2026

Construction begins for the new feeder building.

Summer/fall 2026

New transformer installation.

Fall/winter 2031

Expected project in-service and removal of old feeder section begins.

Fall/winter 2032

Expected project completion.

The schedule will be updated and additional detail will be available as the project advances.

This upgrade will provide increased reliability to the electrical system, replace aging equipment that's nearing end-of-life, and help more of the community switch from fossil fuels to electricity. It will ensure that we can continue to meet the needs of the substation's service area and prepare for future growth in the area.

Get in touch

If you'd like to share your feedback about the project or have any questions, please connect with us.

Email: projects@bchydro.com
Phone: 604 623 4472
Toll free: 1 866 647 3334
 

Get email updates

To receive information about the project by email, please fill out the form below.

Fields marked with * are required.
 

The information collected in this Newell Substation project update subscription form by BC Hydro is collected under the authority of Section 26(c) of the Freedom of Information and Protection of Privacy Act for B.C. Data may be stored outside of Canada. If you have any questions concerning how your personal information is handled, please contact projects@bchydro.com. Unsubscribe from project updates.