Newell Substation upgrade
We're upgrading Newell Substation to improve reliability, address safety risks, and meet projected load growth. This will allow us to continue to provide reliable electricity to about 59,000 homes and businesses in southern Burnaby as well as to other substations.
What's new
Partial Beresford Street closure - transformer delivery
Due to delays in obtaining the municipal traffic permits required for this delivery, the work has been postponed and rescheduled as follows.
New dates: The partial street closure will begin on November 16, 2026 (afternoon) and last until November 19, 2026 (early morning).
On November 17, 2026, a replacement transformer will be delivered to the Newell substation as part of the ongoing upgrade project. Transformers are a critical piece of equipment that convert high-voltage electricity entering the substation into lower voltages that can be safely distributed to homes and businesses.
The transformer will be transported on an oversized trailer measuring approximately 27 metres long by 5.5 metres wide. Due to the oversized dimensions of the load, the Ministry of Transportation and Transit restricts transportation to overnight hours between 12:00 a.m. and 5:00 a.m.
To facilitate delivery of the new transformer, Beresford Street between Griffiths Drive and the crosswalk west of Griffiths Drive, will be temporarily closed to traffic, and parking will not be permitted. Crews will use this space to move the transformer and its components onto a specialized remote-controlled trailer to transport the new equipment safely into the substation.
To make the most of the temporary road closure, we'll also receive several other large pieces of equipment needed for the project.
What to expect
- November 16 (afternoon): Traffic control measures and the Beresford Street closure will be put in place.
- November 17 (12 a.m. to 5 a.m.): The transformer is expected to arrive at the substation.
- Magnolia Terrace may be briefly used as additional maneuvering space during the transfer of equipment into the substation. Traffic control crews will direct access to maintain safety and minimize impacts to the community.
- Equipment unloading and placement activities are expected to be completed by the end of the day on November 18.
- Beresford Street will remain closed until approximately 12 a.m. on November 19, when the empty transport vehicle is permitted to leave the area.
Access information
- Vehicle access to Magnolia Terrace will be maintained via Gilley Avenue during the road closure.
- The Highland Park Line Trail will remain open throughout the operation. We ask that pedestrian and trail users follow all posted signage and directions from traffic control crews to help ensure everyone's safety during these activities.
Transformer removal
The existing transformer is scheduled to be removed from the site in late November/early December 2026. To support this work, temporary no-parking restrictions will be in effect on the south side of Beresford Street within the same work area. Signage will be posted closer to the removal date.
We appreciate the patience and cooperation of the community while we complete this important infrastructure upgrade.
Newell Substation, located at the corner of Kingsway and Griffiths Drive in Burnaby, was built in stages from 1946 to 1955. The substation has been operating reliably for almost 70 years. Newell Substation is connected to seven other substations and serves about 59,000 customers (about 66% residential, 24% commercial, and 11% industrial). The substation takes high-voltage electricity from transmission lines and converts it to the voltages needed to supply power to customers.
We're planning to remove old outdoor equipment that's in poor condition (labelled Feeder Section to be removed in the figure below) and replace it with modern equipment housed in a new feeder building. We'll also replace one of three transformers at the substation as it's reaching end-of-life and make required upgrades to other equipment at site.
Newell substation upgrade project map
Select the project map [PDF, 821 MB] to view it at a larger size.
We'll also install underground infrastructure in Griffiths Drive to the east of the new feeder building and interconnect with existing infrastructure north of the site fence. We'll determine the specific location of the infrastructure and interconnections as studies progress.
Some land outside the fence on the south side of the substation will be used for contractor parking and work zone. During construction a walking path will be available but it will be located further south, closer to the road. After the upgrades are complete, we'll restore the sites not needed for future project work.
These upgrades will ensure that Newell Substation can continue to provide reliable electricity supply to residents, businesses, and other substations.
New feeder building
The new feeder building will be located on the northeast corner of the substation site (see figure above). This location was selected after considering:
- Safety
- Constructability
- Ability to connect to existing equipment
- Environment
- Community impacts
- Cost
Locating the building on the northeast corner:
- Keeps the building within the existing property line,
- Doesn't have permanent impacts to the greenspace south of the fence line,
- Is further from residences, and
- Is more cost effective.
Design of the new building is underway and current renderings are shown below.
| Key dates | Activity |
|---|---|
| Fall 2025 | Vegetation removal. |
| Fall 2025 | Site preparation begins with bumping out the retaining wall in the northeast corner. |
| Summer/fall 2026 | Construction begins for the new feeder building. |
| Summer/fall 2026 | New transformer installation. |
| Fall/winter 2031 | Expected project in-service and removal of old feeder section begins. |
| Fall/winter 2032 | Expected project completion. |
The schedule will be updated and additional detail will be available as the project advances.
This upgrade will provide increased reliability to the electrical system, replace aging equipment that's nearing end-of-life, and help more of the community switch from fossil fuels to electricity. It will ensure that we can continue to meet the needs of the substation's service area and prepare for future growth in the area.
Reports and documents
- Updated construction notice: Transformer delivery and partial Beresford Street closure (November 14, 2026) [PDF, 359 KB]
- Construction notice: Concrete pouring and extended work hours (October 13, 2026) [PDF, 45 KB]
- Project newsletter (September 2026) [PDF, 416 KB]
- Construction notice: Highland Park Line Trail relocation begins July 13, 2026 [PDF, 175 KB]
- Newell Substation information session (June 2026) [PDF, 1.1 MB]
- Open house presentation (January 2025) [PDF, 796 KB]
- Open house presentation (February 2024) [PDF, 611 KB]
- Newell substation project map [PDF, 821 KB]
Get in touch
If you'd like to share your feedback about the project or have any questions, please connect with us.
Email: projects@bchydro.com
Phone: 604 623 4472
Toll free: 1 866 647 3334
Get email updates
To receive information about the project by email, please fill out the form below.
Fields marked with * are required.
The information collected in this Newell Substation project update subscription form by BC Hydro is collected under the authority of Section 26(c) of the Freedom of Information and Protection of Privacy Act for B.C. Data may be stored outside of Canada. If you have any questions concerning how your personal information is handled, please contact projects@bchydro.com. Unsubscribe from project updates.
