McLellan Substation Upgrade
The Surrey/Langley region, one of Canada's fastest-growing areas, is receiving major upgrades at McLellan Substation to meet rising electricity demands. Serving over 49,000 customers, the station at 196 Street and 54 Avenue is being refurbished and expanded to ensure reliable power across the area and to support the growth.
What's new
July 2024
We're currently refurbishing and installing new equipment at McLellan Substation. Planning for the station fence expansion, set for fall 2025, is also underway.
To ensure continued and reliable electricity in east Surrey and Langley City, we're upgrading the McLellan Substation located at 196 Ave and 54 St. The expansion will be completed in two phases:
Phase 1
- Refurbish existing feeder positions with new equipment to ensure continued reliability of power to the Surrey / Langley area.
- Adding new feeder positions to support growth.
- Install a new shunt capacitor bank to relieve voltage constraints to support load growth in the Central Fraser Valley Regional Transmission System.
Phase 2
- Expand the substation in the southeast corner to add a new transformer and associated equipment.
- Add new feeder positions to utilize the additional capacity provided by the new transformer, thereby doubling the capacity of the substation.
McLellan Substation Upgrade
This map highlights the McLellan Substation upgrade area, showing new distribution points, refurbished feeder sections, the new 230/25kV transformer, shunt capacitor bank, and tree removal area.
Select the project map [PDF, 512 KB] to view it at a larger size.
The Surrey/Langley region is one of the fastest-growing regions in Canada. We're investing in upgrades at McLellan Substation, located at 196 Street and 54 Avenue, to meet the region's increasing electricity needs. We serve over 49,000 customers from this station, covering an area extending north to Willoughby, south to the U.S. border, west to Cloverdale, and east to 232 Street.
Timeline | Milestone |
---|---|
Summer 2024 | Start adding new feeder positions to the existing feeder section. |
Fall 2024 | Begin installation of shunt capacitor banks and feeder section expansion. |
May 2025 | Complete Phase 1 work. |
Fall 2025 | Start Phase 2 work with vegetation clearing, followed by ground reinforcement and equipment installation. |
Fall 2026 | Complete shunt capacitor bank installation, transformer and feeder section expansion. |
Late 2029 | Station expansion in-service. |
Reports and documents
- Project factsheet (July 2024) [PDF, 1.4 MB]
- McLellan substation upgrade project map [PDF, 512 KB]
Contact us
If you'd like to learn more about the project, please contact us at:
Email: projects@bchydro.com
Phone: 604 623 4472
Toll free: 1 866 647 3334