Skip to content

   

Second Narrows Crossing project

Second Narrows Crossing project map

Second Narrows Crossing project map

Select the map [PDF, 27.4 MB] to view it at a larger size.
 

The 2L003 and 2L049 transmission lines that span Burrard Inlet at Second Narrows supply electricity to customers in Burnaby and Vancouver. The structures that carry these transmission lines, some of which were built in the 1920s, are at risk of being damaged during an earthquake and don't meet current seismic standards.

What's new

We've completed the alternatives assessment and will upgrade the Second Narrows crossing by upgrading or relocating transmission towers along the current alignment.

We're considering two design options for tower 689 – upgrade the tower in its current location or relocate the tower closer to the North Vancouver shoreline. The other towers will be upgraded, as required, in their existing locations.

We’re working to upgrade, replace, or relocate up to four transmission line structures that cross Burrard Inlet at Second Narrows near the Iron Workers Memorial Bridge so that they will continue to be able to operate in the event of an earthquake.

This upgrade will increase the reliability of the electrical system by upgrading or replacing infrastructure that does not meet seismic standards. It will contribute to the safe and efficient operation of the transmission lines that serve Vancouver and Burnaby.

The leading alternative involves:

  • Reinforcing foundations, including ground improvements.
  • Upgrading structures 687 and 688.
  • Upgrading or relocating structure 689.
  • Assessing structures 690 and 691 and completing seismic upgrades, if required.
  • Painting structures 689 and 690.
  • Constructing an access road to structure 689.

We're considering two design options for structure 689.

  • Design option A – keep the tower in its current location.
    • Improve the ground around the existing foundation.
    • Upgrade the existing foundation.
    • Install a new steel tower at the same location.
  • Design option B – relocate the tower north.
    • Improve the ground under the new foundation.
    • Build new foundation.
    • Install a new steel tower north of the existing tower.

We considered a variety of factors including First Nations interests, environmental and/or archaeological impacts, cost, system reliability, constructability, maintenance, property requirements, stakeholder interests and schedule. Alternative 1 performed best in the evaluation.

We considered five alternatives.

Two alternatives were advanced for further study in the alternatives assessment:

  • Alternative 1 – Upgrade existing structures along the existing alignment (leading alternative).
  • Alternative 2 – Build new transmission structures on a new alignment.
Second Narrows Crossing Project options.

Three alternatives were determined to not be viable and did not advance to the alternatives assessment:

Do nothing.

  • Does not address the issues with the existing structures.

Submarine cable.

  • The south bank is too steep for cables.
  • Much higher cost and longer schedule.
  • New right-of-way likely needed on both sides of the crossing.

Installing a new cable on Iron Workers Memorial Bridge.

  • The bridge can't carry the weight of the power cables.
Key dates Activity
2025 to spring 2027
  • Identify and refine the leading alternative
  • Complete studies (e.g., geotechnical)
  • Complete design to confirm that the leading alternative can be built
  • Identify the preferred alternative (i.e., the alternative that will be built)
Spring 2027 to Spring 2030
  • Complete detailed design
  • Apply for and receive permits and authorizations
  • Issue a request for proposal (RFP) for construction contracts
Summer 2030
  • Start construction
2033
  • Project in service

 

Project reports and documents

Share your feedback

If you'd like to share your feedback about the project and the alternatives being considered, please contact us at:

Email: projects@bchydro.com
Phone: 604 623 4472
Toll free: 1 866 647 3334