For the 2008 LTAP, a targeted update to the 2005 Resource Options Report (filed as Appendix F in the 2006 IEP) has been undertaken for certain resource options where the data has changed significantly. The scope of the Resource Options Update work generally focused on updating cost, technology and potential. Options targeted for updating included those that were commercially proven and affected by the provincial government's BC Energy Plan policies, the latest BCUC Decision on the 2006 IEP/LTAP [PDF, 1.13 Mb], or increases in capital and construction costs.
A three-stage engagement approach has been used to update the resource option information.
Please see the table below for specific session dates and for materials, such as presentations, session notes or reports.
| Stage 1 – Determine Scope | |||
| Scope | Session | July 19, 2007 | Agenda Presentation Session Notes |
Session | July 30, 2007 | Presentation Session Notes | |
| Stage 2 – Update Resources | |||
| Small Hydro | Session | September 12, 2007 | Presentation Session Notes |
| Session | November 19, 2007 | Presentation A Presentation B Session Notes | |
| Report | November 2007 Run-of-River Hydroelectric Resource Assessment for British Columbia (Kerr Wood Leidal) | Report Map | |
| Biomass | Session | September 19, 2007 | Presentation Session Notes |
| Wind | Meeting | December 4, 2007 Wind Integration Project - Status Update Meeting | Presentation [PDF, 85 Kb] |
| Report | February 22, 2008 Assessment of the Energy Potential and Estimated Costs of Wind Energy in British Columbia (Garrad Hassan) | Report [PDF, 1.6 Mb] | |
| Coal-Fired Generation | Report | March 5, 2008 Technology Summary: Clean Coal Power Generation by C0 2 Sequestration (Powertech Labs Inc.) | Report |
Natural Gas-Fired Generation | Report | February 28, 2008 BC Hydro 2008 Resource Options Update Gas-Fired Combustion Turbine Power Plant Costs and Performance Updates (AMEC) | Report [PDF, 147 Kb] |
| Large Hydro | Memo | November 8, 2007 Jordan River Pumped Storage | Memo |
Session | November 28, 2007 | Presentation Session Notes | |
| Site C website | Materials related to the Peace River Site C Hydro Project can be found online. | Site C | |
| Stage 3 – Report Results | |||
| Results | Session | December 4, 2007 | Presentation Handout Session Notes |
Last Modified: Jun 3, 2008