Construction Schedule Make Text Larger Make Text Smaller Print This Page

 
MilestoneDates
(subject to change)
Nisga'a Nation, First Nations, public consultationOngoing
Application for an EA Certificate accepted by EAOApril 2010
EA Certificate receivedFebruary 2011
Noninvasive pre-construction activitiesFall 2010; ongoing
Design-build contractSummer 2011
Right-of-way clearing startJanuary 16, 2012
Construction completionSpring 2014
NTL fully commissioned and in-serviceSpring 2014
Restoration and cleanupSummer 2014

 

Northwest Transmission Line Project Map

NTL - a new line starting from Skeena Substation (near Terrace) to a new substation near Bob Quinn Lake