| Milestone | Dates (subject to change) | | Nisga'a Nation, First Nations, public consultation | Ongoing | | Application for an EA Certificate accepted by EAO | April 2010 | | EA Certificate received | February 2011 | | Noninvasive pre-construction activities | Fall 2010; ongoing | | Design-build contract | Summer 2011 | | Right-of-way clearing start | January 16, 2012 | | Construction completion | Spring 2014 | | NTL fully commissioned and in-service | Spring 2014 | | Restoration and cleanup | Summer 2014 |