The extensive work to upgrade the station involves eight different projects and eight of the ten generating units at GMS.
The most substantial are the replacement of turbines in five units.
Eight projects on eight of 10 generating unitsThe replacement of turbines in five units will take several years to complete, with each unit taking seven months. Because of the province’s reliance on GM Shrum, the turbines will be replaced in stages to ensure any units are not out-of-service during the peak load season – the winter – when demand in the province is the highest. Use the anchor links below to view a short description and status update of each project:
Project: Units 1 to 5 Turbine RehabilitationThe need for renewalThe 1960s era turbines in GMS Units 1 to 5 must be replaced to ensure ongoing reliability, availability and operational flexibility of these units, which represent 12 per cent of BC Hydro’s power production. Another benefit of the project will be an improvement in turbine efficiency and capacity. Modern turbine design will provide an additional 177 gigawatt hours of energy annually with the same water usage. The current maximum capacity per turbine is 261 megawatts. The new turbines will be limited to the current capacity because of other existing equipment capacity constraints and existing water licence limitations. It will ultimately allow the generating units to one day operate at a capacity of 310 megawatts. However, this capacity increase will require additional equipment upgrades, which are not currently planned, and approval from the Ministry of Environment. What’s involved?The first stage of project implementation consists of the design and modelling of a turbine. In July 2010 stage two of the project was awarded to Voith Hydro and the project has now entered the implementation phase. The second stage includes shop fabrication of the turbine followed by site construction, installation and start-up of the turbine. The first turbine unit is expected to be operational in November 2012, and work on the other four units will continue sequentially until all five units are in service by mid 2015. The fabrication of components for the first unit is nearing completion and is expected to be delivered to GMS in March 2012. Work at site to install the first unit will then begin. Manufacturing of components for the second unit is well underway. The turbine components are being manufactured in Canada, Brazil, China, Romania and Italy. Project: Units 1 to 4 Generator Stators ReplacementThe generator stators (the stationary part of the generating unit that converts the mechanical energy of the rotor into electrical energy) in Units 1 to 4 were also built in the 1960s and are due for replacement. Installation of the first unit began four years ago. All four units were completed when the last unit was brought into service this summer.
|
Last Modified: Feb 2, 2012