The project involves working around and within the confines of the existing plant while it is in full operation, except for an approximate six-week shutdown which is expected to begin in early May.
It's anticipated that the gas turbine will be back in service by mid-July 2011 and that the project will be finished by November, 2011.
Work on schedule, shifting into next phaseEarly site preparation work was completed by a local Fort Nelson First Nation company, Eh-Cho Dene Enterprises, in summer 2009. Prior to work beginning, soil sampling and testing was carried out and a soil and environmental management plan was successfully implemented. All equipment packages required for the project have been secured. Assembly of the air-cooled condenser and the once-through steam generator is currently underway. The next phase of construction and plant commissioning by the General Installation Works contractor was due to start in January 2011. It is anticipated that the gas turbine will be back in service by mid -July 2011. |
Last Modified: Aug 17, 2011