Mica Units 5 & 6 Projects

BC Hydro employee watching over construction at Mica Dam

Time to install two units

We're installing two generating units at Mica Generating Station to ensure B.C. continues to have electricity to meet peak demand. Mica was Designed as a six-unit facility, but installation of Units 5 and 6 had been deferred.

Overview and updates

BC Hydro is working to install two additional approximately 500 MW generating units into existing turbine bays at Mica Generating Station.

The Mica Unit 5 project will also require construction of a new series capacitor station near the midpoint of the existing Mica to Nicola 500 kV transmission line needed to reliably deliver the additional electrical generation at Mica.

The target in-service dates for Mica Unit 5 is October 2014 and the target in-service date for Mica Unit 6 is October 2015.

Project updates