NTL: Schedule and activities

Image of tower being erected on Northwest Transmission Line Project
Milestone Dates
(subject to change)
Environmental Assessment Certificate received February 2011
Transmission line design-build contract awarded
September 2011
Substation contract awarded June 2012
Right-of-way clearing started January 16, 2012
Construction completed June 2014
Commissioning
Completed
Restoration and clean-up Summer/fall 2016


Northwest Transmission Line Project Map