Skip to content

Metro North Transmission Project

What's new

Over the past year, we've been reviewing the Metro North Transmission Project to ensure that we're making this investment at the right time.

In our last update to stakeholders, in July 2019, we confirmed that the recent load forecast showed a lower load increase than expected.

A further analysis of this forecast has determined that the Metro North Transmission Project won't be needed until about 2035; therefore, we have decided to cancel the project. Going forward, we'll continue to monitor the load forecast and transmission system every year to confirm the timing of any project needed to reinforce the system.

This decision will have no impact on the reliable supply of electricity to our customers in this area.

Thank you for your participation while this project was underway.

We're planning to build an additional 230 kilovolt (kV) transmission line(s) between Coquitlam and Vancouver, to increase electrical transmission capacity and strengthen the reliability of the network.

This improvement could be built with a combination of overhead lines – using existing rights-of-way (the land under and around our power lines) wherever possible – and underground circuits in city streets. Modifications to existing substations will be required to support the new line(s).

Our current transmission system is approaching its limit for reliability. Without these improvements, we could see potential outages or service interruptions to many homes and businesses.

The Metro North Transmission Project is part of a long-term strategy to meet load growth and ensure reliability of the transmission network for the Metro Vancouver area.

The transmission system improvement proposes:

  • About 10km of overhead lines and 20km of underground cables from Meridian Substation in Coquitlam through Anmore, Port Moody, and Burnaby to the Mount Pleasant Substation in Vancouver.
  • Replacement of existing overhead lines in Anmore and Port Moody, resulting in fewer, taller poles than existing in these areas.
  • An overhead crossing of Burrard Inlet, within the current right-of-way.
  • A new underground route through Burnaby and Vancouver.

Of the three alternatives studied, this was selected as it has:

  • fewer overall residents and property owners potentially impacted by construction.
  • lower seismic and construction risks.
  • the most capacity for the investment.

Adding additional transmission lines to the regional transmission system is the most cost-effective solution to address increasing electricity demand in Metro Vancouver. Some of the benefits include:

  • New transmission will also increase electrical transmission capacity and strengthen the reliability of the Metro Vancouver electricity network.
  • It will benefit residential and business customers by supporting growth, reducing the risk of overloading aging cables, and facilitating redistribution of electricity in the event of circuit outages.
  • Our current transmission system is near its limit and without these improvements the network faces reduced service reliability. Under certain conditions this reduced reliability could mean outages for the equivalent of 30,000 homes and businesses and service interruption for the equivalent of 90,000 homes and businesses.

Consultation began in Summer 2013, with the leading alternative identified in October 2016.  

The project is on hold. We plan to have a new date for the project early next year, based on a new load forecast.

Activity Timing
Identification
Initial & additional studies, and select alternative
2013 to 2016
First Nation and community consultation commences Summer 2013
Public open houses

January to February 2014 (Burnaby, Coquitlam, Port Moody, and Vancouver)

January 2015 (Anmore)

June 2016 (Anmore)

Stakeholder meetings Since 2013, we have had over 90 meetings with interested stakeholders.
Confirm leading alternative October 2016
Definition
Preliminary design & BC Utilities Commission review process initiated
2018 to 2020
Public open houses: preliminary routing options for Vancouver & Burnaby March 8 and 9, 2017
Grandview cut walking & cycling bridge event August 26 and 29, 2017
Preferred route for Burnaby and Vancouver

November 4, 2017 (Vancouver)

November 6, 2017 (Burnaby)

November 18, 2017 (Vancouver)

November 25, 2017 (Vancouver)

November 25, 2017 (Burnaby)

Ongoing consultation 2018 to 2020
Certificate of Public Convenience and Necessity Application to B.C. Utilities Commission
TBD
Implementation
Final design, procurement, construction, and commissioning TBD
Operation TBD


We manage our projects in a financially, socially, and environmentally sustainable way. We're working with independent environmental consulting firms, to identify impacts and develop mitigation strategies now to inform environmental management and monitoring activities should the project proceed to construction. We'll report on these findings and strategies within our application to the BC Utilities Commission.

We're looking at:

  • Air quality
  • Noise
  • Fish, fish habitat and aquatic biology
  • Vegetation including at-risk plant species
  • Wetland habitat, health and function
  • Wildlife and wildlife habitat
  • Visual landscapes
  • Lane and resource use including parks, recreational and tourism areas, utilities and land use plans
  • Contaminated sites
  • Economy
  • Community
  • Heritage resources

Since 2013 we've held over 90 meetings with interested stakeholders and have hosted 15 public open house events.

Input from local and regional governments, transportation authorities, community groups, and others has informed the project design and route. We have also included feedback from our ongoing engagement with First Nations, from meetings with affected property owners, and the findings from technical work done to date.

Information by municipality

Anmore

Burnaby

Coquitlam

Port Moody / Burrard Inlet Crossing

Vancouver

Reports & documents

Metro North Transmission project update – October 2017 [PDF, 601 KB]

Open house summary report – November 2017 [PDF, 2.2 MB]

Contact

projects@bchydro.com
604 623 4472
Toll free: 1 866 647 3334