How the Program Was Developed

BC Hydro sought input from potential developers, First Nations, customers and other stakeholders early in the development of the Standing Offer Program in order to influence the design of the Program, and to build a mutual understanding of interests.

The consultation process included:

  • A June 2007 invitation by BC Hydro for written comments on the draft Program Rules and draft Standard Form Electricity Purchase Agreement;
  • During July and early August 2007, 10 information sessions at several locations in the province to provide further information on the Program and give an opportunity for feedback on the Program and the draft documents.
  • The receipt of over 800 comments by First Nations and stakeholder on the draft Program documents by August 3, 2007.
  • A November 29, 2007, information session in Vancouver to review revisions to the draft Program Rules and draft Standard Form Electricity Purchase Agreement.

Regulatory review process

BC Hydro filed its application for proceeding with the Standing Offer Program with the British Columbia Utilities Commission (BCUC) on December 14, 2007, pursuant to section 45 of the Utilities Commission Act. BC Hydro subsequently filed amendments to its application on January 18, 2008.

During February 13-5, 2008, a Negotiated Settlement Process took place involving BC Hydro, intervenors and BCUC staff. On March 19, 2008, the BCUC issued Order No. G-43-08 approving the Negotiated Settlement Agreement and the expenditures required to implement the Standing Offer Program for the next two years.

The BCUC directed BC Hydro to file final form Standing Offer Program documents (Rules, Standard Form EPA and Application Form) in a timely manner.

Standing Offer Program development timeline

PhaseTimeline
SOP announced, draft Rules and draft Standard Form EPA issued for commentsJune 20, 2007
Stakeholder information sessions and Written Comments on draft documentsJune 20 to August 3, 2007
Revised draft documents releasedNovember 14, 2007
Stakeholder information session on revised draft documentsNovember 29, 2007
Submission of section 45 application to BCUCDecember 14, 2007
BCUC regulatory review process
  • Commission Information Requests to BC Hydro
  • Registration deadline for Intervenors and Interested Parties
  • Intervenor Information Requests to BC Hydro
  • Responses to Commission and Intervenor Information Requests by BC Hydro
  • Program Application Workshop and Negotiated Settlement Process

 

January 11, 2008
January 14, 2008
January 18, 2008
February 1, 2008

February 13-15, 2008
BCUC Order approving the Negotiated Settlement AgreementMarch 19, 2008
Program launchApril 11,  2008

Documents published during the development of the program

Document Date Posted
Standard Form EPA black-lined [PDF, 282 Kb] April 11, 2008
Program Rules black-lined [PDF, 540 Kb] April 11, 2008
Revised Draft Program Rules [PDF, 1.9 Mb] January 18, 2008
Revised Draft Program Rules black-lined [PDF, 1.9 Mb] January 18, 2008
Revised Draft Standard Form EPA black-lined [PDF, 1.8 Mb] November 23, 2007
Revised Draft Standard Form EPA [PDF, 541 Kb] November 23, 2007
Revised Draft Program Rules [PDF, 1.7 Mb] November 14, 2007
Revised Draft Program Rules black-lined [PDF, 1.6 Mb] November 14, 2007
Lender Consent Agreement Form [PDF, 238 Kb] November 14, 2007
Revised Draft Program Rules [PDF, 1.6 Mb] July 5, 2007
Draft Application Form [PDF, 987 Kb] June 29, 2007
Draft Standard Form EPA [PDF, 1.4 Mb] June 20, 2007
BC Hydro Code of Conduct Guidelines
EcoLogo M Letter  [PDF, 431 Kb] June 29, 2007
Network Upgrade Security Form [PDF, 92 Kb] June 29, 2007
Development Report Form [PDF, 58 Kb] June 29, 2007
COD Certificate Form [PDF, 58 Kb] June 29, 2007

For more info

Please email us your question or join our mailing list.

Last Modified: Sep 2, 2009