We've just released a report that shows that more than a third of contractors hired for Site C to date are from the Peace River region – and that 80% are from B.C. And crews fighting a West Kelowna wildfire that took out several BC Hydro power poles caught a break with the timely arrival of cool, moist weather.
One third of Site C hires local: report

One third of Site C hires local: report

A BC Hydro report shows that of the more than 1,400 contractors hired so far for work on Site C, 651 are from the Peace River region and 80% are from B.C.

See the story at energeticcity.ca
Hard work and weather contain Bear Creek wildfire

Hard work and weather contain Bear Creek wildfire

West Kelowna fire crews worked alongside BC Hydro crews trying to restore power after fire led to outages and evacuations near Kelowna.
See the story in the Kelowna Capital News
Photo of the week

Photo of the week

A transformer might seem like an attractive spot for a cat-nap, but the summer sun proved a little too hot for this feline. Last weekend, we were notified that a cat was on top one of our poles in the Merritt area. Our crews responded to the call and were able to safely bring the cat back down to earth.
Log in to MyHydro    Accounts & Billing    Energy Savings    Safety & Outages
Contact Us