New station has close to five times capacity of old site
CRANBROOK – BC Hydro has completed the $95-million redevelopment of the Aberfeldie Generating Station, located on the Bull River, 35 kilometres east of Cranbrook. The dam and generating station is now completely operational and generating electricity during the 2009 freshet.
The Aberfeldie Redevelopment Project is part of BC Hydro's Resource Smart program, and includes a new powerhouse with an approximate capacity of 24 megawatts. The project also includes a new surge tower and switchyard, a new penstock, as well as improvements to the existing water intake, dam and access road.
"Investing in this heritage asset will assist in helping to meet our current and future energy demand in British Columbia," said Blair Lekstrom, Minister of Energy, Mines and Petroleum Resources. The Aberfeldie Dam and Generating facility will now produce enough energy to supply 10,500 residential customers annually. "This reduces BC Hydro's need for importing additional energy and supports BC Hydro's purpose – reliable power at low cost for generations."
The original Aberfeldie station was only a five megawatt generating facility. It was constructed in 1922 and parts of it were rebuilt in 1953. The wood stave penstock and major generating equipment had reached their end of life and were no longer serviceable.
The original station ceased operation in October 2006 in preparation for its redevelopment, which received British Columbia Utilities Commission approval in February of 2007. The project was completed with the support and efforts of the Ktunaxa Nation, regulatory agencies, local government, Knight Piesold Limited, Western Versatile Construction Corp., Andritz VA Tech Hydro Canada Ltd., local contractors, stakeholders and BC Hydro employees.
"BC Hydro worked with all of these groups to identify and address all of the environmental impacts of the project to the highest environmental standards," said Bob Elton, BC Hydro President and CEO. "The project also included the signing of an agreement with Ktunaxa Nation that included contract work and employment opportunities."
To minimize the project's impact on fish and wildlife, disturbed areas were re-vegetated to a natural state and a side channel for fisheries and aquatic life was constructed downstream of the new powerhouse. "The side channel will compensate for habitat impacts related to the change in flow in the section of the Bull River between the Aberfeldie Dam and Generating Station," said Doug Baker, BC Hydro Project Manager. "BC Hydro will release minimum flows year round to ensure habitat is available in the canyon between the dam and powerhouse during the winter low-flow period."
Media can download photos of the construction of the new Aberfeldie Generating Station and a photo of the historic facility by going to our Facilities Image Library.
Media may request raw footage by contacting Dag Sharman, BC Hydro Media Relations, 604 623 4022.
Contact:
Diane Tammen
East Kootenay Community Relations
Phone: 250 489 6862
Dag Sharman
Media Relations
Phone: 604 623 4022
Quick Facts – Aberfeldie Generating Station
Last Modified: Sep 21, 2009