VANCOUVER – BC Hydro today filed a Revenue Requirements Application (RRA) for fiscal years 2009 and 2010 with the British Columbia Utilities Commission (BCUC), which includes a $3.4 billion capital program to renew and upgrade Hydro dams and electricity infrastructure.
The two-year rate application will include a rate increase which, for the majority of BC Hydro residential customers, will amount to $5 or less per month for each year of the application. Even with this increase, BC Hydro residential customers will continue to enjoy among the lowest electricity rates in all of North America.
"British Columbia's population and economy are growing at the same time that our infrastructure is aging," said Bob Elton, BC Hydro President and CEO. "For many years we have relied on the power generated from our heritage hydro assets built in the 1950s, '60s and '70s. These generating facilities are aging, with many of the components and systems nearing the end of their life. In order to ensure these facilities continue to provide a stable supply of electricity for British Columbians for generations to come, we need to reinvest in them to extend their life, adding capacity where possible."
Over the next two years alone, BC Hydro is proceeding with signifi cant capital work to renew and upgrade hydroelectric infrastructure at several facilities, including:
In addition, BC Hydro will be making investments in the province's transmission system, through BC Transmission Corporation, and in the province's distribution system, which delivers power to homes and businesses. BC Hydro will also invest in new clean, renewable electricity sources through long-term purchase agreements and will enhance Demand Side Management Programs to work towards BC's Energy Plan goal of meeting 50 per cent of future incremental resource needs through conservation by 2020.
The proposed general rate increase will be 6.56 per cent in the first year and an additional 8.21 per cent in the second year. The RRA requires the approval of the BCUC and will be subject to a public hearing in the summer of 2008. With the approval of the BCUC, rate changes become effective on an interim basis on April 1, 2008.
BC Hydro is also proposing to lower the deferral account rate rider from 2 per cent to 0.5 per cent, which effectively reduces the cumulative rate impact to 13 per cent over the two years. The rate rider, which will continue to be listed on customer bills as a separate line item, is intended to pay down non-controllable costs such as additional market energy purchases required as a result of low water inflows. These are costs that BC Hydro has deferred over the last several years in order to avoid sudden rate fluctuations.
"We recognize that even a modest rate increase has an impact on our customers. However, customers can partially or even fully offset this increase by making some changes to the way they use electricity," added Elton. "BC Hydro is committed to helping our customers do just that. We have and will continue to expand and increase our Power Smart programs, tools and incentives to help British Columbians achieve their conservation goals."
Later in February, BC Hydro will also file a Residential Inclining Block (RIB) rate application as referenced in the 2008 Speech from the Throne. The RIB will create a two-step rate structure intended to encourage conservation among residential customers. This rate structure, which is subject to approval by the BCUC, will be revenue neutral to BC Hydro.
| Susan Danard |
| Media Relations |
| Phone: (604) 623-4220 |
Many of BC Hydro's existing power-generating facilities were built in the 1950s, 1960s and 1970s. Some were originally built as far back as 1922. While there have been upgrades over the years, these facilities are in need of refurbishment and expansion if they are to continue providing British Columbia with electricity.
To address this aging infrastructure, BC Hydro is investing signifi cant expenditures to maintain the reliability and expand the capacity of its generating facilities. BC Hydro is also funding a number of projects on the transmission system (through BC Transmission Corporation), which moves electricity from these generating facilities to B.C.'s major load centres, and on the distribution system that provides customers with the power they need.
Over the next two years alone, BC Hydro plans to invest $3.4 billion in the province's generation, transmission and distribution systems, and other facilities. Signifi cant capital work is being planned or contemplated at several generating stations and dams, including the Mica and W.A.C. Bennett dams, which are among the largest in the world.
The following are some of the major projects either underway or set to begin to help ensure that BC Hydro can meet the electricity needs of British Columbians:
Revelstoke Generating Station (Unit 5) – $280-$350 million
Peace Canyon Generating Station (Stator Replacement, Rotor Modification, Turbine Overhaul) – $141 million
Gordon M. Shrum Generating Station (Stator Replacement) – $75-$91 million
Mica Generating Station (Stator Replacement) – $97 million
Aberfeldie Generating Station (Redevelopment) – $95 million
Coquitlam Dam (Seismic Improvement Project) – $66 million
Interior to Lower Mainland Transmission Project – $600 million
Vancouver Island Transmission Reinforcement Project – $287 million
Substations and feeders
Storm Response and Preparation
In the wake of the 2006/07 storm season, one of the worst on record, BC Hydro initiated a new five-year, $265 million program to improve system resiliency and outage communications. Among the projects: increasing vegetation management, under-grounding or realigning some portions of circuits, strengthening cables and wires, and providing additional automation and redundancy.
Last Modified: Feb 20, 2008