In This Section

VI CFT Questions & Answers By Number

 
1. Access to VI CFT and EPA
2. Date of Pre-Qualification Workshop
3. Role of Independent Reviewer and Bidder Access to Independent Reviewer
4. VIGP Election and Bidder Disqualification
5. Purpose of Bidder Registration Fee
6. Partnership in Bidder Registration
7. Eligibility of Small Projects
8. Date of Pre-Qualification Workshop
9. Purpose of Bidder Registration Fee
10. Payment of Bidder Registration Fee
11. Payment of Bidder Registration Fee
12. Location and time of Pre-Qualification Workshop
13. Purpose of VI CFT and BC Hydro's Role in VI CFT
14. Eligibility of a Hydro Project in the VI CFT
15. Monitoring VI CFT Process
16. Arrangements for VIGP Site Visits
17. Definition of Eligible Energy
18. VIGP Site Elevation
19. Allowable Number of Attendees for Pre-Qualification Workshop
20. Late Registrations
21. Financial Information for Pre-Qualification Submission
22. Definition of "Must-Run" Facility
23. Interconnection Cost Allocation
24. Communicating with Independent Reviewer
25. Bidder Providing Gas Transportation
26. Payment of Interconnection Studies
27. Network Upgrade Costs Provided to Bidders
28. Submission of Document Comment Forms
29. IR Review of BCTC Network Upgrade Costs
30. Eligibility of DSM or Load Curtailment Projects
31. Opportunities to Comment on EPA
32. Mandatory Criteria Evaluation Process
33. Involvement of Independent Reviewer in Pre-Qualification Process
34. Engineering, Procurement, Construction and Operation Agreements
35. Changes to Bidder and/or Project
36. Information Required for Special Purpose Entities
37. Upper Limit for Aggregate Capacity
38. Eligibility of Generation Projects not Located on Vancouver Island
39. Sales to Third Parties
40. Changes to CFT Schedule
41. Water as a Fuel
42. VIGP Option for BC Hydro
43. Are VIGP Permits Appealable?
44. VIGP Permits and Due Diligence
45. VIGP: First Nations Benefit Agreement
46. VIGP Site Due Diligence
47. Exclusion of Certain Assets in VIGP Asset Purchase
48. VIGP Project Site
49. VIGP Interconnection Study Requirements
50. VIGP Facilities Agreement and Interconnection Agreement
51. Contracting Out of Interconnection Contsruction Work
52. Interconnection Studies for Alternate Sized Projects
53. Interconnection Study Fee
54. Sharing Interconnection Study Costs
55. Timing of Pre-Qualification and Inteconnection Study Application
56. Bidder Input on Scope of Preliminary Interconnection Study
57. Provision of Security to Sellers by BC Hydro
58. Quarterly Demonstration Tests and De-Rating a Project
59. Tolling for Natural Gas Project
60. Switching from "Must-run" to Dispatchable Capacity
61. Relationship between Milestone Security and Guaranteed COD
62. Gas for Start-up and Testing of Gas-Fired Tolling Plants
63. Gas Pressure Quality for Gas-Fired Tolling Plant
64. BC Hydro Purchase of Excess Energy
65. Decline of the Operating Security During the EPA
66. Assessing the Heat Content of Gas
67. Natural Gas Indices for EPA Pricing
68. Quarterly Demonstration Tests
69. Release of Evaluation Spreadsheets
70. Application and Refund of Liquidated Damages
71. Off-Island Generation
72. Number of Starts per Year for a Must-Run Project
73. Normalising Net Portfolio NPVs
74. Release of Evaluation Spreadsheets
75. Value of Capacity in Peak Months
76. Discount Rate for NPV Calculation
77. Evaluation Methodology: Gas and Electricity Forecasts
78. Greehouse Gas Offsets and Green Credits
79. Gas Transportation and Commodity Costs for Non-Gas Fired Projects
80. Gas Delivery to Different Locations
81. Future Calls
82. Late Gas Delivery for Gas-Fired Tolling Plant
83. Sale of Pre-COD and Excess Electricity
84. Pricing for Duct Firing in Gas-Fired Tolling Plants
85. Off-Island Generation
86. Fast Tracking VIGP Permit
87. Payment for Pre-COD Electricity
88. Evaluation Methodology: Capacity and Energy
89. CFT Section 17.2
90. Definition of Fuel
91. Value of Capacity for Off-Peak Hours on Vancouver Island
92. Access to VIGP Data Room for Non-VIGP Bidders
93. Changes to Pre-Qualified Project
94. Normalisation Over a 25-year Term
95. Gas Transportation Costs
96. Fuel Supply Certainty for Dependable Capacity
97. Q&As on VI CFT Website
98. Unavailable Service Providers
99. Provision for Comments on the EPA
100. Tender Security and Final Permits
101. Gas Tolling and GSX
102. Virtual VIGP Data Room
103. Deadline for VIGP Data Room and Site Visits
104. Definition of Force Majeure in the VIGP Assets Agreements and VI CFT EPA
105. List of VIGP Data Room Documents
106. Evaluation Methodology: Gas and Electricity Price Assumptions
107. Documentation Not in VIGP Data Room
108. "Regulatory Outs"
109. Credit Default by BC Hydro
110. EPA Divestature by BC Hydro
111. GSX Status
112. Transmission Capacity on Vancouver Island
113. Evaluation Methodology: COD Date and Term Assumptions
114. VIGP Permit Risk
115. Financial Statements for Pre-Qualification
116. Financial Capacity for Pre-Qualification
117. Curriculum Vitae References Required for Pre-Qualification
118. Treatment of VIGP Asset Price versus Salvage Value
119. VIGP Benchmark and Evaluation Process
120. Bidders Combining Their Projects
121. Non-Gas Fuel Risk
122. Annual Forecast of Capacity Needs
123. EPA Information Requirements
124. Advancement of Project's COD
125. Invoice Payment
126. Quarterly Capacity Tests
127. Price for Pre-COD Electricity and Provision for Gas for COD Testing
128. Foreign Exchange Rate Risk Over the EPA Term
129. Project Specific EPA Changes
130. Seasonal Pricing
131. Release of Evaluation Spreadsheets
132. Treatment of Greenhouse Gas Costs in Evaluation
133. BC Hydro Payment of LDs if Low Cost Portfolio Not Selected
134. Assignment of the EPA
135. Is the Evaluation Methodology Biased in Favour of VIGP?
136. Release of Evaluation Spreadsheets
137. Treatment of Energy in Evaluation Methodology
138. VIGP Asset Price and Salvage Value
139. Release of Evaluation Spreadsheets
140. Vancouver Island Dependable Capacity Requirements
141. Bidders Locating Facilities on BC Hydro's Lands
142. Responsibility for Future GHG Cost Mitigation
143. Carbon Tax Flow-Through to BC Hydro
144. Off-Site Emission Reduction Rights
145. Value of Transmission Deferral Credit
146. Duct Firing Pricing and Peaking Capability of Non-gas Fired Projects
147. Selling Additional Capacity to BC Hydro During the Term of the EPA
148. Provision of Pre-Qualification Workshop Transcript
149. Exchange Rate Used in VIGP Application to BCUC for a CPCN
150. Contacting BCUC Regulators
151. Pre-Qualification Proposals Involving a Proposed Partner
152. Necessary Supporting Documentation for Proposed Partnerships
153. Posting a Word Version of the EPA
154. Basis for VIGP Emissions Calculations
155. Executed VIGP Confidentiality and Restricted Use Agreement
156. Arranging VIGP Data Room Visits
157. Consequences for Not Meeting 97% Availability
158. Corporate Experience and Section 9.8 of the CFT
159. Formula Used to Adjust the Guaranteed Heat Rate (GHR)
160. Engineering, Procurement, Construction and Operation Agreements
161. Installing the Evaluation Spreadsheet for Multiple Users
162. BC Hydro Senior Executive Responsible for the VI CFT
163. BCUC Commissioner Responsible for Reviewing VI CFT
164. Performance Parameters of the VIGP Plant
165. Evaluation Methodology: Different VIGP Configurations
166. Basis for VIGP Summer Fired Heat Rate
167. Monthly Availability Calculations
168. Use of the Transmission Deferral Credit in Evaluation Model
169. Comparing Net Tender Cost to Original VIGP/GSX Option
170. Error in Evaluation Manual for "Must-Run" Description
171. Weighted Average of Baseload Heat Rate and Minimum Turndown Heat Rate
172. Maximum Number of Starts per Year to Determine Must-Run Projects
173. Gas Transportation Adder for Gas-Fired Projects
174. List of Permits Required for VIGP Project
175. Status of all VIGP Permits
176. Expected Issuance Dates for VIGP Permits
177. Comparing Net Tender Cost to Original VIGP/GSX Option
178. Dispatch Worksheet Logic
179. Pre-Qualification Proposals Involving a Proposed Partner
180. Communication to Registered Bidders
181. Ability to Curtail Output from April through September of Each Year
182. Ability to Curtail Output from April through September of Each Year
183. Inclusion of Interconnection Facilities in VIGP Permitting Process
184. BC Hydro Building VIGP
185. Consumer Price Index (CPI) Used to Convert to Nominal
186. Tendering VIGP Plant Defined in Design Basis Memorandum (DBM)
187. Curtail Output for a 6 Month Period
188. Project Selection and BC Hydro Tax Exempt Status
189. BC Hydro Cost Assumptions for VIGP
190. Guaranteed Heat Rate (GHR) Formula to Reflect Actual Weather
191. Treatment of 150 MW "Short" Position
192. Pricing Forecasts to Accommodate Duct Firing
193. Discount Rate Used in Evaluation
194. Changing Pre-Qualified Bidder's Legal Structure
195. Qualifying as Peaking Facility
196. Application of Gas Fuel Compression Cost
197. Changes to VIGP Plant After Pre-Qualification
198. Addressee for Financial Statements
199. Completion of Section 3 of the Pre-Qualification Form
200. Locating Bidder Comments and/or BC Hydro Responses on the CFT Web page
201. Disclosure of Bidder's Projects
202. New Deadline for the Pre-Qualification Form
203. When will New Evaluation Spreadsheet be Available
205. BC Hydro Actions Following BCUC 23 January 2004 Letter
206. Load Reduction as Back-Up Energy Source
207. Calculation of NPV Using Five NPV Outputs for that Tender
208. Application of a "Gas Transport Adder" to 10-Year and 25-Year Term
209. Release of "Gas Transport Adders"
210. Release of Final "Gas Transport Adders"
211. Different Table of "Gas Transport Adders" for Dual-Fuel Projects
212. Acceptable Capacity for Duct-Firing
213. Expected Date for Release of Start Frequency Table
214. Duct-Firing Activity Must Meet Definition of "Dependable Capacity"
215. Definitions for Hydro and Wind Projects
216. VIEC Interconnection Application
217. Timeframe to Answer Questions
218. Inclusion of all Applicable Taxes, Wheeling and Duties in Analysis
219. Release of Evaluation Standards for Dual Fuel Capable Projects
220. Procedure for Quarterly Capacity and Heat Rate Levels Test for Duct Firing
221. Submitting a Tender with Generation at More than One Site
222. Installation of Spare Turbine and Back-Up Service for Other Suppliers
223. Output Requirements in Summer Months
224. Transmission System Upgrade for Capacity Projects North of Dunsmuir
225. Impact of Recent IPP Contracts on Available Transfer Capabilities on VI
226. Network Upgrade Costs for VIGP Interconnection Facilities Study
227. VIGP Curtailment: Network Upgrades and 1L112
228. VIGP Single Circuit Connection
229. Compression of Transmission Construction Period for VIGP Interconnection
230. BCTC's Role in the Transmission Permitting Process
231. Timing of BCTC's Update on the VIGP Interconnection Study
232. Forced Outage Example
233. Independent Reviewer Concerns with CFT
234. Cost of Independent Reviewer
235. Impact of Statistical and Financial Measurements on Analysis
236. Purpose of Cell P58 "Gas Fuel Compression Cost"
237. Start-Up Costs when Dispatch MWH is Zero
238. Start-Up Costs for Dispatchable Hog Fuel-Fired Plant with Low Energy Charges
239. Issuance of Revised Portfolio and Tender Spreadsheets prior to 29 March 2004
240. Definition of "Clean and New"
241. Mandatory 25 Year Term
242. Adjusting the Portfolio Size
243. Allowance for Transportation Fuel Gas
244. Least Cost Methodology and Portfolio Methodology in the CFT
245. Allocation of Costs if Buyer Declines Arbitrated Extension
246. Meaning and Implications of "Generation Capital Recovery"
247. Updated Requirements for Availability or Forced Outage Rates
248. Additional Workshops prior to Pre-Qualification Submissions
249. Compliance with Permits if VIGP Turbine Generators Not Inside a Building
250. Provide Drawings in Original Drawing Format
251. Fuel Supply Certainty and Guarantees for Wind
252. Consideration of Power Smart Savings in Interconnection Upgrades
253. Responsibility for Gas Pressure for Tolled Projects
254. Industrial Customer Upgrade Requirements
255. Detailed Technical and Performance Data for Fuji Turbine
256. Modifying Tender Spreadsheet and Definition 108 (b) of Appendix 1 of the EPA
257. Locating Fuji Purchase Contract on Data Room CD
258. Availability of Interconnection Study Submitted to BCTC
259. Black-lined VIGP Transfer Agreement
260. Amending Information in "Full Tolling Option Designation and Information Form"
261. Using "Gas-Fired Fuel Risk Allocation Election Form" for Separate Projects
262. Responsibility for Paying Network Upgrade Costs
263. Other Bidders Assuming a Pre-Qualified Bidders Project
264. Definition and Application of Force Majeure
265. Clarification on Charges Incurred by BC Hydro
266. Locating Index File for VIGP Data Room Disk 2
267. Sumitomo Contract Guarantees
268. Timing for Release of VIGP Benchmark
269. Communications with BCUC
270. Documentation Provided on VIGP Data Room Disk 2
271. Qualified Bidders Amalgamating Projects for Tender Submission
272. Price Premium for 25-Year Gas Price
273. BC Hydro's Use of VIGP Decision Gas Price Forecast
274. Resolving Different Gas Price Forecasts
275. Issuance of CFT Tender Guidelines
276. Geological Study of VIGP Site
277. Errors when Using PortfolioVI Model
278. Expediting Air Permit Issuance
279. Affiliation of Bidders with Respect to "No Collusion"
280. Deadline for Project-Specific Comments on the Final Form Agreements
281. Inability to View PDF Document
282. EIA Forecast in Terms of Sumas Index
283. Obligation of BC Hydro to Supply Start-Up Gas Upon Seller's Request
284. Extending Tender Submission Date
285. Fuji Steam Turbine Drawings in CADD Format
286. Higher Outputs from the Steam Turbine Generator
287. Providing the WMA Permit to Bidders
288. Treatment of Wastewater
289. Firm or Interruptible Transportation from Terasen
290. Permits to Allow Provision of Water
291. Request for Documents not Found in VIGP Data Room
292. Implications of the Gas Price Forecast in Tender Evaluation
293. Tender Spreadsheet: Units in Cell I37
294. Correspondence between Bidders and P&T
295. Availability Calculation: Clarification of "Percentage Availability"
296. Availability Calculation: Article 3.6
297. Demonstration of Plan Availability if BC Hydro Has Not Scheduled Energy
298. Reference to Section 5.2(e) in Appendix 5
299. Gas Price Forecast and NYMEX Forward Curve
300. Power Smart Study of Mill Operations
301. Appendix 5 and Necessary Equipment Information
302. Requirement for Appendix 5 Pre-Tender
303. Tender Security for Tender With Multiple Projects
304. Tender Security for Multiple Tenders
305. Tender Security for Multiple, Mutually Exclusive Tenders
306. Bidder and Project Information To Submit at Tender
307. Pending Claims or Litigation Relative To VIGP
308. Quarterly Financial Statements Required as Part of Tender
309. Rights to a Site in Order to Pass Development Risk Assessment
310. Paying for Physical Interconnection to Terasen System
311. Providing Gas Transportation and Commodity before COD
312. Relief for Insufficient Delivery of Gas Pre-COD
313. Gas-Fired Tolling Project Passing Development Risk Assessment
314. Terasen Assurance of Capacity to Meet Pre-COD Commissioning and Testing
315. BC Hydro Guarantee of All Permits Required For VIGP
316. Arranging and Paying for Interconnection to BCTC Transmission System
317. Consequence of that Interconnection Being Delayed
318. Paying for “Preparatory Work” In BCTC’S Preliminary Study Report for VIGP
319. Arranging and Paying for Required Network Upgrades
320. Consequence of Network Upgrades Being Delayed
321. Provision of “Domestic Gas” for Gas-Fired Tolling Plants
322. Status Of GSX
323. Assessing Fuel Supply Certainty
324. Submitting a Bid that Includes Dual Fuel Capability
325. Types of Maintenance
326. Seller’s Failure to Meet Milestones
327. Operating and Maintenance Costs
328. Necessary Details Concerning VIGP Permits
329. GHG Offset Ownership Rights
330. Obligations Arising Under EA Certificate
331. First Nations Consultations
332. GHG Emissions Burdens and Benefits
333. Benefits Agreement and Further First Nations Consultation
334. Corrections/Refinements Required in Calculation of Amonthly
335. Paying for Demonstration Tests
336. Dispatchable/Non Peaking Capacity Plant in Both HLH And LLH
337. Correct Units in Reporting Interruptible Gas Transportation Cost
338. Overall Inclusive Cap on All Liabilities in Aggregate
339. Requirement to Replenish Security after Draw
340. Reduce LD Amounts
341. Reimbursement of Bidder Costs if BCUC "Approval" Not Obtained
342. Claim for Liquidated Amount is Disputed
343. Price Adjustment if Seller Becomes a Regulated Public Utility
344. Financial Responsibility for Emissions Liability
345. BC Hydro Commitments with Labour Unions or Associations
346. Material Changes in Respect to EA Certificate Condition 4
347. Governmental Consent Required to Complete VTA
348. Termination of P&T Agreements in Accordance with their Terms
349. $14 Million Investment Commitment in EA Application
350. Demonstration Tests Costs Allocation Under EPA
351. Force Majeure and Reseting Demonstrated Capacity
352. Resetting Major Maintenance Interval
353. Termination Payment
354. Availability Calculation and Planned Outages
355. Availability Calculation: Definition of Term "N"
356. Availability Calculation: Applicability of Definition (b) for EAFj
357. Noise Specification in EAO
358. Who Pays for VIGP GHG Offsets
359. VIGP Benchmark Addendum
360. GHG Mitigation
361. VIGP Site Access Agreement for Geotechnical Testing
362. P&T Supply Agreements and Ownership of Water Equipment
363. Actual Exchange Rate Used in Gas Price Forecast
364. Gas Transportation Agreements to VIGP Tolling Projects
365. Level Playing Field Between Gas and Non-Gas Projects
366. Minimum Ambient Temperature for Fuji Steam Turbine
367. Public Availability of the VI Upgrade Plan
368. Treatment of GHG in the Evaluation Methodology
369. Potential Conflict with a Bidder's Financial Advisor
370. Redundant Information in Tender Forms
371. Completion of Start-Up
372. Units for Capital Costs
373. Notification of Passing Development Risk Assessment
374. Lower Capacity While Operating on Distillate
375. Temperature and Humidity Curves While Using Distillate
376. Change to Definition of EAF
377. Clarification on Payments for Physical Interconnection to Terasen System
378. Cut-Plane D Capacity Deficiency in 2007/08 Only
379. Discounting Cut-Plane Upgrade Costs to Match Portfolio Capacity
380. Consideration of Transmission Capacity Committed to Uncertain 2003 GPG Projects
381. Use of Generation Shedding to Avoid Cut-Plane Upgrades
Search Questions and Answers