July 24, 2008 June 6, 2008 |
BC Hydro issued the Phase I RFP on February 6, 2008.
The web content is intended for the Proponents registered to participate in the Phase I RFP. BC Hydro will update these pages on an ongoing basis. It is the sole responsibility of each Proponent to review the pages on a regular basis and to identify new postings, including Addenda and revised versions of Phase I RFP documents. BC Hydro assumes no liability or obligation to proponents who are unaware for any reason of the web content.
Proponents participating in the Phase I RFP need to familiarize themselves with relevant documents and other pertinent information.
| Event/Activity | Timeline |
|---|---|
| Issue of EPA Term Sheet | February 29, 2008 |
| Proponents Submit Application to BC Hydro (for Distribution System-connected Projects) for a Preliminary Interconnection Study (section 12). | February 29, 2008 |
| Registration | March 7, 2008 |
| Submission of Customer GBL data | March 7, 2008 |
| Proponents Submit Application to BCTC (for Transmission System-connected Projects) for a Feasibility Interconnection Study (section 12) | March 7, 2008 |
| Proponent Information Session | March 26, 2008 |
| Filing of Preliminary Interconnection Study agreements with BC Hydro for Distribution System-connected Projects (4:00 p.m. PPT) | March 31, 2008 |
| Filing of Feasibility Interconnection Study agreements with BCTC for Transmission System-connected Projects (4:00 p.m. PPT) | April 7, 2008 |
| Notice to Customers of GBL | May 2, 2008 |
| Issue of Specimen EPA | May 7, 2008 |
| Proposal submission (4:00 p.m. PPT) | June 10, 2008 |
| Release of Feasibility Interconnection Study or Preliminary Interconnection Study, as applicable | June 20, 2008 |
| Proponents notified of short list (optional) | June 27, 2008 to July 15, 2008 |
| Negotiation, Final Evaluation and EPA signing Phase** | July 2, 2008 to October 15, 2008 |
*Schedule reproduced from section 7 of the Bioenergy Call RFP. Certain capitalized words and phrases used in this schedule are set out in Appendix 1of the Bioenergy Call RFP. Please refer to these definitions for clarity.
**EPA awards will be subject to Section 71 approval by the British Columbia Utilities Commission.