Procurement & Supplier Opportunities Make Text Larger Make Text Smaller Print This Page

For work opportunities at Ruskin, consult BC Bid

Consistent with BC Hydro's procurement practices, public competitive procurement opportunities for work at Ruskin have been advertised on BC Bid.

Ruskin project work will include:

Right Abutment Stage II

This work will involve reinforcing the right (i.e., west) bank of the dam with a specially designed barrier wall to manage water seepage during and after a seismic event.

Spillway Gates supply contract

This contract was awarded under the existing partnership agreement between BC Hydro and HMI Construction Inc.

This work will involve final design, manufacturing and supply of five new Spillway Gates.

Contract A (Upper Dam and Powerhouse Structure Upgrade)

This work will involve a seismic upgrade of the dam and the powerhouse, including construction of new piers, installation of new spillway gates, construction of a two lane bridge and powerhouse superstructure upgrade, installation of the new powerhouse crane and a new elevator.

Contract B (Powerhouse Completion Contract)

This work involves powerhouse telecommunications, protection and control, electrical and mechanical upgrades, the powerhouse seismic upgrade not completed in Upper Dam and Powerhouse Structure Upgrade contract, intake gates, tunnels and penstocks rehabilitation, draft tube gates installation and left abutment slope stabilization.

The majority of the packages associated with the Ruskin Project were advertised publicly on BC Bid and went through a competitive RFP process.

It is BC Hydro intent to package the civil work and equipment supplies to ensure safe and efficient implementation of the project with the minimum impact on the community and the environment.

Status of major contracts

The British Columbia Utilities Commission (BCUC) granted a Certificate of Public Convenience and Necessity for the Ruskin Dam and Powerhouse Upgrade Project on March 30, 2012. The decision means BC Hydro may now begin construction. BC Hydro expects to begin project construction this spring.

Right Abutment Stage IIAwarded to Golder Associates
Turbine and GeneratorAwarded to Voith Hydro Inc.
Contract A
(Major Civil Work)

RFP#943 closed November 17, 2011.

Bid closed. Negotiations underway.

Contract B
(Balance of Plant)
Expected to be posted to BC Bid early in 2013

Information about the results of the public competitive procurement process for major Ruskin Project packages will be made available to the public and organizations in accordance with the Freedom of Information and Protection of Privacy Act, legislation and BC Hydro governing acts and procurement policies.

Local opportunities

BC Hydro is working with local businesses and the community to facilitate opportunities for local involvement. For example, the Mission Chamber of Commerce has developed a Mission Handbook for Major Projects. BC Hydro will be distributing this handbook to its local offices and contractors working in the area.

For more information on the handbook, please contact the Mission Chamber of Commerce.

Contact us

If you would like to learn more about the project, please contact us by: