Construction Schedule Make Text Larger Make Text Smaller Print This Page

Twenty hours a day, six days a week for six years

The Ruskin Dam and Powerhouse Project is expected to take six years to complete, based on two 10-hour shifts, six days a week.

With the approval of the project by the British Columbia Utilities Commission, construction is expected to start in spring 2012. The tentative schedule is:

DescriptionDates
Seismic upgrades of the Right Bank2012 - 2013
Dam upgrades including piers and spillway gates2013 - 2017
Seismic upgrade of the powerhouse structure2012 - 2013
Replacement of the powerhouse equipment2013 - 2017
Relocation of the switchyardSometime after 2014
Project completion and closeout2018