Mica Units 5 & 6 Projects

Mica

IT'S TIME TO INSTALL TWO ADDITIONAL UNITS

BC Hydro is reinvesting in Mica Generating Station to ensure British Columbia continues to have electricity it needs during peak times of demand.

Originally designed as a six-unit facility, the installation of generating Units 5 and 6 were deferred. Now that additional capacity is needed, BC Hydro will install the two additional units.

 

 

Overview and updates


BC Hydro is working to install two additional approximately 500 MW generating units into existing turbine bays at Mica Generating Station.

The Mica Unit 5 project will also require construction of a new series capacitor station near the midpoint of the existing Mica to Nicola 500 kV transmission line needed to reliably deliver the additional electrical generation at Mica.

The target in-service dates for Mica Unit 5 is October 2014 and the target in-service date for Mica Unit 6 is October 2015.

Project updates


Project background

More capacity will help meet peak-period demand in B.C.

What's being done

Five steps for each unit, from draft tube to switchgear.

Quick Facts header

Cost

Between $700 and $800 million

Completion

2014 & 2015

What's being done

Installation of two 500-megawatt generating units.

Benefits

Will add about 1,000 MW of generation capacity, enough to power 80,000 homes during peak periods of demand.

Cool fact

Expected to create 800 person years of direct employment.

Last Modified: Feb 8, 2012