Construction Schedule
With construction underway in spring 2012, the Ruskin Dam and Powerhouse Project is expected to take six years to complete.
Project construction is underway and is scheduled as follows:
| Description | Dates |
|---|---|
| Seismic upgrades of the Right Bank | 2012 - 2013 |
| Dam upgrades including piers and spillway gates | 2013 - 2017 |
| Seismic upgrade of the powerhouse structure | 2012 - 2013 |
| Replacement of the powerhouse equipment | 2013 - 2017 |
| Relocation of the switchyard | Sometime after 2014 |
| Project completion and closeout | 2018 |