PRES: Schedule

Project schedule

ACTIVITY DATE (SUBJECT TO CHANGE)
Study/consult on alternatives Fall 2013 to Fall 2015
Select leading alternative Fall 2015
Further studies and consultation on leading alternative 2016 to 2017
Permit applications and reviews
2017 to 2018
Start of construction 2018
Target in-service date Between 2020 and 2022


Current and upcoming activities

The majority of our work is investigative in nature and is being done to help us finalize the route and design for the transmission lines. We are currently in the area working on:

  • refining the preliminary transmission line route,
  • developing access plans to the proposed transmission lines,
  • developing clearing plans for the proposed transmission lines, and
  • investigating geotechnical conditions along the proposed route.

We recently completed the centerline survey of the proposed transmission line route and archeological and environmental surveys.