Project Schedule

Maps

More detailed maps are available in Section 4 of the Environmental Assessment Application.

Key Project Milestones

Milestone Date
Commenced Public/First Nations Consultation Summer 2006
Initiated Environmental Assessment Process December 2006
Filed application for a Certificate of Public Convenience and Necessity (CPCN) with BC Utilities Commission (BCUC) Fall 2007
CPCN granted by BCUC August 2008
Environmental Assessment application filed with BC Environmental Assessment Office (BCEAO) October 2008
Environmental Assessment Certificate granted June 2009
Transmission Line Design-Build Contractor Selected Summer 2011
Planned in-service date January 2015

 

*Transmission Line Preliminary Construction Schedule as of December 2012

For construction management purposes, the 247 kilometre transmission line route has been divided into five sections starting at the Nicola Substation near Merritt.

Activities By Section Section 1 Section 2 Section 3 Section   4 Section   5
Section Boundaries Nicola Substation to Salem Creek Logging Road Salem Creek Logging Road to Spuzzum Spuzzum to Hicks Creek Hicks Creek to Stave Falls Stave Falls to Meridian Substation

Right-of-way preparation, including land surveys, upgrading existing and constructing new access roads as required, vegetation/tree clearing, equipment set-up

March 2012 to June 2013 August 2012 to June 2013 November 2012 to late November 2013 June 2012 to July 2013 June 2012 to early October 2013

Construction of transmission line, including building foundations, constructing towers and stringing conductors (wires)

April 2012 to February 2014 August 2012 to September 2014 March 2013 to late September 2014 Mid-September 2012 to mid-July 2014 Mid-September 2012 to April 2014
Right-of-way restoration ongoing from February 2014 September 2014 September 2014 July 2014 April 2014

*This preliminary schedule is subject to change.

Interior to Lower Mainland Project Map

The ILM Project includes building a new 250 kilometre long 500 kilovolt (kV) transmission line mostly along an existing right-of-way between the Nicola Substation near Merritt and the Meridian Substation in Coquitlam.

ILM Transmission Line Construction Map

Select the map below to view larger image.