DCAT: Schedule and activities

dcat-transmission-work-helicopter-trees-660x216-assets.jpg

The DCAT project was placed into service in November 2015.

Construction schedule

Milestone Timing
Site prep at Bear Mountain Terminal Complete

Clearing and access road construction

Foundation construction

Clearing, Sundance Lakes Substation site

Complete

Site prep at Sundance Lakes Substation

Civil work, Bear Mountain and Sundance Lakes substations

Complete

Structure installation/stringing

Electrical equipment installation at substations/commissioning

Complete
In-service date November 2015